Hydrogen Charged Enertainer
Edmondson Park North Commuter Car Park, Australia
Background
Introduction & Project Information
- Installation date: Dec 2022
- Loads: 2 Tower cranes, 2 Concrete booms
- Enertainer Model: Enertainer L x1
- Input current to the Enertainer: 20 to 55 amps
91%
CO2 reduction (vs. 2 X 350 kVA generators)*
~Zero
noise and air pollution with hydrogen
Internet connected continuous monitoring
Stable and reliable supply of energy
*Assuming a hydrogen generator CO2 emission intensity of 0.1875 kg per kWh and diesel emission intensity of 2.64 kg per litre
The Challenge
The Solution
Results
“Successfully recharging the Enertainer using a blue hydrogen-powered generator was a significant step forward in establishing a cleaner and more pleasant construction site. The Enertainer has replaced four diesel generators, resulting in the saving of 72 tons of CO<sub>2</sub> emissions, 40,000 litres of diesel, and AUD$48,000 per month. The Enertainer emerges as a game-changer, better for the environment, greener and safer. We can’t wait to see it being implemented on our other projects, further reducing A W Edwards carbon footprint, and committing to achieving net zero carbon emissions in 2050.”
Mr. Raymond Hudd
Project Manager, A W Edwards
Download Case Study
Discover how our Enertainers can enhance efficiency while protecting the environment and reducing costs.
Download Case Study
Discover how our Enertainers can enhance efficiency while protecting the environment and reducing costs.