Supporting Multiple Pieces of Equipment at Once

On Muk Street, Sha Tin, Hong Kong

Location

Contractor

Project Type

Location

Sha Tin, Hong Kong

Project Type

Residential Development

Main Contractor

CR Construction

Background

Introduction & Project Information

  • Developer: Housing Authority
  • Delivery Date: 16 June 2021
  • Loads: 1 Tower crane, 1 Hoist, 1 Builder lift
  • Enertainer Model: Enertainer L
  • Input Current to the Enertainer: ~25-35 amps
  • 86%

    lower operating cost (vs. 400 kVA generators)1

    80%

    CO2 reduction (vs. 400 kVA generators)2

    99%

    uptime through project period

    Zero

    air quality pollutants leading to better a working environment

    1Assuming a diesel price of HK$11.0 per litre.

    2Assuming a CO2 emission intensity of 0.39 kg per kWh (Source: CLP Sustainability Report 2021)

    The Solution

    Results

    "We are happy with the performance of the Ampd Enertainer which has helped us power multiple pieces of high power equipment on a very limited electricity supply. By replacing diesel generators, the Enertainer significantly reduced our operating costs and carbon emissions by reducing our need for diesel generators. The Enertainer is a high quality, reliable product and we will definitely deploy more at our future sites."

    Mr. Oscar Yu
    Plant Manager, CR Construction

    Download Case Study

    Discover how our Enertainers can enhance efficiency while protecting the environment and reducing costs.

    Download Case Study

    Discover how our Enertainers can enhance efficiency while protecting the environment and reducing costs.