Powering Two Tower Cranes, Superstructure

North Point, Hong Kong

Location

Contractor

Project Type

Location

North Point, Hong Kong

Project Type

Superstructure of a 2 million sq. ft., 45-floor building

Main Contractor

Hip Hing Construction Company Ltd.

Background

Introduction & Project Information

  • Delivery Date: 7 February 2020
  • Loads: 2 Tower Cranes (1 x Liebherr 357HC-L 12/24, 1 x Liebherr 357HC-L 18/32)
  • Enertainer Model: 1 x 400 kVA
  • Maximum Input Current to the Enertainer: 30 amps
  • 85%
    81%
    424 amps
    90%+

    The Solution

    Results

    "I’ve been looking for a way to reduce our reliance on diesel for a while, so when the chance to use the Ampd Enertainer came along, I was excited. The result delivered beyond the original idea. Not only did it reduce our emissions but also our operational costs and noise. It also proved extremely easy to use, so the project team was very pleased. In addition, we conducted some trials to test the recharging efficiency and the energy storage capacity of the Enertainer. The results exceeded our expectations."

    Herman Lee
    Senior Manager, Plant and Logistics, Hip Hing

    Download Case Study

    Discover how our Enertainers can enhance efficiency while protecting the environment and reducing costs.

    Download Case Study

    Discover how our Enertainers can enhance efficiency while protecting the environment and reducing costs.